Japan's Rapidus struggles with SRAM production on 2nm node, threatening 2027 timeline

The government-backed chipmaker has successfully demonstrated working transistors but faces significant hurdles integrating them into functional memory cells, putting its mass production schedule at risk.

7 min read
Rapidus reportedly struggles to produce working SRAM on its 2nm node, putting 2027 mass production at risk

Rapidus, Japan's semiconductor startup, is grappling with substantial difficulties in fabricating operational SRAM cells on its 2nm-class process, which employs EUV lithography. According to reporting, the company missed a key milestone to show working SRAM cells during summer 2026, even as the Japanese firm produced semiconductor test structures at its Hokkaido facility in mid-2025. The company is also reportedly contending with particle contamination inside its cleanroom. These challenges threaten the government-backed company's target to launch mass production in 2027.

Rapidus misses SRAM milestone

Bloomberg's account brings troubling news for the Japanese chipmaker. Rapidus started producing test structures containing 2nm-class Gate-All-Around (GAA) transistors at its IIM-1 facility in Hokkaido in July 2025, roughly 16 months before the present time. The company stated at that time that its prototype transistors showed the anticipated electrical characteristics, signaling that its manufacturing equipment and core process steps functioned properly.

Then we had a testing and July 10th we confirmed a major milestone: we successfully obtained electrical characteristics of 2-nanometer node GAA transistors. We can see the transistor actually works.

Atsuyoshi Koikem, chief executive of Rapidus, at Hot Chips 2025

Rapidus
(Image credit: Rapidus)

Yet fabricating individual transistors proves far simpler than creating functional integrated circuits (ICs) containing numerous interconnected components. Per Bloomberg sources, Rapidus was expected to deliver functional static random-access memory (SRAM) cells by summer 2026, but has not reached this objective. The report does not specify whether Rapidus faces difficulties with single SRAM cells, larger memory arrays, or achieving satisfactory electrical characteristics and manufacturing yields, leaving room for interpretation.

SRAM holds critical importance in contemporary processors, serving as cache memory and constituting other integrated memory structures capable of housing hundreds of millions of bitcells. Additionally, SRAM arrays serve as valuable instruments for early process assessment, as their repetitive nature exposes manufacturing defects, transistor inconsistencies, and other complications that may escape detection during isolated transistor evaluations.

A standard 6T SRAM bitcell incorporates six transistors: two cross-coupled inverters (accounting for four transistors) plus two access transistors. These transistors also demand contacts and local interconnects, along with connections to wordlines, bitlines, and power rails (VDD and VSS). A complete SRAM macro additionally requires peripheral circuits, including row decoders, sense amplifiers, write drivers, and control logic, making a 256 KB SRAM macro a notably intricate IC. Consequently, semiconductor manufacturers typically employ both SRAM cell arrays and SRAM macros as primary vehicles for assessing, tracking, and validating process technologies across multiple development phases. Furthermore, achieving low defect density in SRAM macros proves essential for strong yields in SRAM-heavy chip designs.

The significance of SRAM renders Rapidus' reported struggles particularly troubling given its stated intention to commence commercial production in 2027. While Rapidus has not confirmed delays in mass production using its 2nm fabrication process, in a discussion with the Japan Times, Rapidus officials indicated the company was progressing toward mass-producing chips in the second half of fiscal 2027, which concludes on March 31, 2028. Previously, Rapidus had outlined its production targets without designating calendar years or fiscal years, which conventionally would have meant the calendar year.

Time is running out

Before commencing mass production for customers, Rapidus must establish functional SRAM cells, combine them into larger structures, reach satisfactory manufacturing yields, validate its process technology, and subsequently launch risk production roughly a year prior to high-volume manufacturing (HVM).

Rapidus
(Image credit: Rapidus)

Semiconductor manufacturers typically do not make public detailed schedules and milestones for SRAM development in relation to new manufacturing technologies. However, TSMC regularly shares updates on its upcoming nodes by disclosing performance and yield metrics for a 256 Mb SRAM array or '256 Mb SRAM yield on an internal product-like vehicle.' For instance, TSMC's N2 demonstrated over 80% of its target device performance and more than 50% yield on a 256Mb SRAM test chip in April 2023. By April 2024, the process had progressed to over 90% of its target device performance and more than 80% SRAM yield. Roughly half a year before mass production commenced, in May 2025, N2 transistor performance approached 100%, while 256 Mb SRAM average yield exceeded 90%. In contrast, Rapidus has not disclosed any SRAM progress, and Bloomberg reports that the company has failed to generate functioning static random access memory cells, indicating that its SRAM yield stands at 0%.

Although no established guideline dictates that a company must possess a functional SRAM array or macro N quarters before commencing mass production of chips incorporating that array or macro, the reported setback clearly leaves Rapidus with constrained time to accomplish its vital development objectives before launching mass production by the conclusion of fiscal 2027.

Exceptional complications

Manufacturing 2nm-class chips featuring GAA transistors and extreme ultraviolet lithography presents extraordinary complexity, even for seasoned chipmakers. To date, only Intel, TSMC, and Samsung have initiated mass production of chips employing nodes that depend on GAA devices. Differing from FinFETs, GAA transistors contain multiple vertically arranged silicon nanosheets enclosed by gate materials, which enhances electrostatic control but introduces supplementary manufacturing obstacles. Additionally, extraordinarily minute feature dimensions demand exceptional rigor in deposition, etching, lithography, and process management. For Rapidus, which commenced operations in 2022 and depends on process technology intellectual property from IBM, replicating these processes reliably in a newly constructed fab constitutes an extraordinarily demanding undertaking.

Rapidus
(Image credit: Rapidus)

One conceivable difficulty involves selective etching of silicon-germanium (SiGe) layers that partition silicon nanosheets throughout the manufacturing process. These sacrificial layers require removal without harming the silicon channels or producing substantial alterations to their proportions. Incomplete etching risks leaving residual material between nanosheets, whereas excessive etching can diminish channel thickness or heighten surface irregularity. A scholarly article released by imec identifies nanosheet release as among the critical hurdles in GAA manufacturing, particularly because inconsistencies in channel geometry can influence transistor behavior and dependability.

EUV lithography itself generates supplementary complications. At extraordinarily diminished dimensions, stochastic phenomena connected to photon uptake, resist composition, and subsequent pattern transfer can generate inconsistencies in feature proportions, edge irregularity, and sporadic absent or malformed features. Such imperfections can compromise essentially everything, encompassing transistor gates, contacts, and interconnects. A company named Fractilia focuses exclusively on stochastic controls. Although isolated test transistors may perform satisfactorily, circuits incorporating millions of interconnected components face substantially heightened vulnerability to malfunctions stemming from stochastic imperfections.

Another probable difficulty pertains to inner spacer development. These minuscule dielectric constructs electrically separate the gate from the source and drain areas. Their production demands meticulous lateral etching of SiGe accompanied by dielectric application. Inconsistencies in spacer proportions can modify effective gate length, parasitic capacitance, leakage current, and transistor behavior. A scholarly work published in Nanomaterials in January 2026 demonstrates that even minute variations in etching parameters can alter spacer proportions and nanosheet integrity, which potentially introduces electrical inconsistency that grows particularly problematic in SRAM configurations.

Gate stack assembly represents yet another conceivable source of complications. GAA production demands uniform application of gate dielectrics and metal substances surrounding multiple nanosheets, encompassing restricted gaps between them. Inconsistencies in material thickness, interfaces, and effective metal work function can modify transistor threshold voltages, which presents minimal difficulty for isolated transistors or diminutive test designs. However, in SRAM configurations, substantial variations among nominally equivalent transistors can diminish read, write, and retention margins, which might render cells incapable of functioning dependably at their designated voltages and substantially contract the manufacturing process window.

Contact resistance, interconnect imperfections, and particle contamination can introduce further complications to circuit assembly. Bloomberg specifically mentions that Rapidus is striving to strengthen dust and particle management in its cleanroom. Under typical circumstances, there might exist no correlation between contamination and the SRAM difficulties the company faces. However, a distinguishing characteristic of IIM-1 involves its application of an unconventional grid-based wafer transportation mechanism to facilitate its single-batch processing and boost the speed of expedited processing. Implementation of this mechanism creates uncertainty regarding whether the novel infrastructure has undergone adequate contamination and dependability assessment, although, once more, a transportation mechanism by itself could not account for zero (or near-zero) SRAM yield.

On-track for 2027?

Rapidus reportedly maintains that it continues pursuing mass production in the second half of fiscal 2027. Nevertheless, absent demonstration of functional SRAM and subsequent larger integrated circuits, doubts regarding its capacity to manufacture commercially feasible 2nm chips will endure.

Source: Tom's Hardware · Reporting supplemented by The Silicon Ledger staff.